Sorry, no Flash player installed!

Projects - Legal & Commercial

Cutlers Gardens Building 9, London, EC1

Client: City Office LLP
Architect:
Fletcher Priest Architects
Services Consultant: Roger Preston & Partners
Contract Period: 15 weeks
Contract Value: £1.5 Million

In spring 2006, Faithdean Plc commenced the refurbishment of 30,000 sq ft of office space over two floors on a negotiated basis. Initially, a strip out of densely fitted out offices including removing screed topping to increase floor to ceiling space and mechanical, electrical services.

The works rolled into a refurbishment to Category A specification including raised access floors, metal pan suspended ceilings, new VRF air conditioning and new lighting to latest Cibse guidelines.

The contract value was in excess of £1.5 million and the works were completed within the tight 15 week programme.